一种计及地线影响的输电线路可靠性动态评估方法
CSTR:
作者:
作者单位:

(1.中国南方电网有限责任公司超高压输电公司贵阳局,贵州 贵阳 550003; 2.输配电装备及系统安全与新技术国家重点实验室(重庆大学),重庆 400044)

作者简介:

易永亮(1982-),男,硕士,高级工程师,研究方向为输电线路类设备运维、检修管理;E-mail:65890516@qq.com
熊小伏(1962-),男,博士,教授,博士生导师,研究方向为智能电网、电力系统保护与控制、电力系统风险评估及气象灾害预警;E-mail:cquxxf@vip.sina.com
徐望圣(1976-),男,本科,工程师,研究方向为输电线路类设备运维、检修管理。

通讯作者:

中图分类号:

基金项目:


A dynamic evaluation method of transmission line reliability considering the effects of ground wire
Author:
Affiliation:

(1. Guiyang Bureau of EHV Transmission Company, China Southern Power Grid Co., Ltd., Guiyang 550003, China;2. State Key Laboratory of Power Transmission Equipment & System Security and New Technology, Chongqing University, Chongqing 400044, China)

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    雷击、冰灾等极端气象事件是导致输电线路故障的主要原因,输电线路的架空地线在夏季的防雷作用以及冬季更易覆冰的特点直接影响线路的可靠性水平。因此有必要研究地线对输电线路可靠性的影响及分析方法,并提出一种计及地线影响的输电线路可靠性动态评估方法。以“月份”作为时间尺度,对地线自身和输电导线逐月故障率分别统计并进行拟合。分析夏季、冬季地线状态对输电导线可靠性的影响,并引入相应的修正系数对输电导线故障率进行修正。利用全概率公式对线路停运概率进行计算,得到了与地线及导线故障率有关的线路全年逐月停运概率函数。算例验证了所提方法的可行性。

    Abstract:

    Extreme meteorological events such as lightning and ice disaster are the main reason of transmission line fault. Overhead ground wire is of lightning protection effect in summer and is easier to be iced than conductor in winter, and it directly affects the reliability of transmission line. It is necessary to study the effects of ground wire on transmission line reliability and the corresponding analysis method. This paper proposes a dynamic evaluation method of transmission line reliability which considers the effects of ground wire. ‘Month’ is taken as time scale rather than ‘year’ and the monthly failure rates of ground wire and conductor are respectively statistically calculated and fitted. The effects of ground wire status both in summer and winter on the reliability of transmission line are analyzed respectively, and the corresponding correction coefficients of conductor failure rate are introduced. Total probability formula is adopted to calculate the outage probability of transmission line, and the monthly outage probability function of whole year is obtained, which is related to both of the failure rate of ground wire and the failure rate of conductor. Finally, a specific sample is used to explain the method and the feasibility is verified.

    参考文献
    相似文献
    引证文献
引用本文

易永亮,熊小伏,徐望圣,等.一种计及地线影响的输电线路可靠性动态评估方法[J].电力系统保护与控制,2017,45(10):77-84.[YI Yongliang, XIONG Xiaofu, XU Wangsheng, et al. A dynamic evaluation method of transmission line reliability considering the effects of ground wire[J]. Power System Protection and Control,2017,V45(10):77-84]