引用本文:张桦,魏本刚,李可军,等.基于变压器马尔可夫状态评估模型和熵权模糊评价方法的风险评估技术研究[J].电力系统保护与控制,2016,44(5):134-140.
ZHANG Hua,WEI Bengang,LI Kejun,et al.Research on risk assessment technology based on Markov state evaluation model for power transformer and entropy-weighted fuzzy comprehensive evaluation[J].Power System Protection and Control,2016,44(5):134-140
【打印本页】   【下载PDF全文】   查看/发表评论  【EndNote】   【RefMan】   【BibTex】
←前一篇|后一篇→ 过刊浏览    高级检索
本文已被:浏览 6699次   下载 3196 本文二维码信息
码上扫一扫!
分享到: 微信 更多
基于变压器马尔可夫状态评估模型和熵权模糊评价方法的风险评估技术研究
张桦1, 魏本刚2, 李可军3, 梁永亮3
1.重庆大学电气工程学院,重庆 400044;2.上海市电力公司电力科学研究院,上海 200437;3.山东大学电气工程学院,山东 济南250061
摘要:
为建立有效的电力变压器设备风险评估方法,针对变压器故障机理的复杂性和不确定性特征,提出了基于状态检修和马尔可夫过程的变压器全态状态评估模型。利用分指标研究变压器缺陷严重度,结合变压器分部位故障频率计算模型,采用熵权模糊计算量化变压器设备风险等级,构建设备风险评估矩阵,给出了一种新的变压器运行风险评估方法。仿真程序实例计算结果表明,所提方法能够准确计算变压器各组成部分的风险值,并获得针对性的维修策略,变压器风险评估结论是准确、有效的。
关键词:  电力变压器  马尔可夫过程  熵权模糊综合评价  风险评估  维修策略  故障频率
DOI:10.7667/PSPC151240
分类号:
基金项目:
Research on risk assessment technology based on Markov state evaluation model for power transformer and entropy-weighted fuzzy comprehensive evaluation
ZHANG Hua1, WEI Bengang2, LI Kejun3, LIANG Yongliang3
1.School of Electrical Engineering, Chongqing University, Chongqing 400044, China;2.Electric Power Technical Research Institute, SMEPC, Shanghai 200437, China;3.School of Electric Engineering, Shandong University, Jinan 250061, China
Abstract:
To build an effective assessment method for the risk of electric power transformers, the full condition model of transformer based on condition-based maintenance (CBM) and Markov Process is established, considering the complexity and uncertainty of transformer fault. The research method of classified index is used for confirming the severity of transformer defects. Combined with the calculation model for subcomponent fault frequency, entropy-weighted fuzzy method is adopted to quantify the serious degree. Based on the above research the assessment matrix is established. Then a new assessment method for the risk of electric power transformers is given. The simulation program is compiled, and a case is analyzed by the risk assessment technology. The calculation result concludes the risk value and maintenance strategy. Empirical results show that the approach proposed is available and effective.
Key words:  power transformer  Markov Process  entropy-weighted fuzzy comprehensive evaluation  risk assessment  maintenance strategy  fault frequency